About the project
The project will be integrated into the existing Golden Pass LNG import terminal. It will include the addition of liquefaction facilities and upgrades to the existing terminal.
The current Golden Pass LNG terminal facilities include five 155,000 cubic meter LNG storage tanks, two marine berths capable of offloading various sized ocean-going LNG carriers, and process facilities capable of regasifying LNG to produce approximately 2 billion standard cubic feet of natural gas per day.
The export project includes construction of three liquefaction process trains. Each process will have a nominal output of approximately 5.2 million metric tons per annum (MTA), associated treatment, power and utility systems, and interconnections to existing import facilities and controls. Golden Pass would also make modifications to the existing facilities, expand the facility’s storm protection levee system, and increase other various safety and security assets.